Upstream's test target exits 0 even when tests fail, so patch it
to report failures; 744 line break tests currently fail upstream.
Details
Details
Diff Detail
Diff Detail
- Repository
- R11 FreeBSD ports repository
- Lint
Lint Not Applicable - Unit
Tests Not Applicable
Event Timeline
Comment Actions
BTW, I haven't bumped PORTREVISION as the package remains unchanged. Please let me know if I should, and I'll do it promptly.
Comment Actions
You don't really need to patch the test suite to exit with failure if it does not pass, as the make test target is mainly for human operators to look at.
That said, it's your choice and it's ok to do it if you prefer that.
No PORTREVISION bump needed.
Comment Actions
Yeah nobody uses that as only about half the test suites actually pass. Good luck with that.
Comment Actions
People certainly do and just because you don't know and/or care doesn't make it right correct (it's been in for over 2 years now).
Your mentee is doing the right thing, thanks @kfv