Index: head/en_US.ISO8859-1/htdocs/releases/10.2R/schedule.xml =================================================================== --- head/en_US.ISO8859-1/htdocs/releases/10.2R/schedule.xml (revision 46719) +++ head/en_US.ISO8859-1/htdocs/releases/10.2R/schedule.xml (revision 46720) @@ -1,184 +1,181 @@ ]> &title; $FreeBSD$

Introduction

This is the release schedule for &os; &local.rel;. For more information about the release engineering process, please see the Release Engineering section of the web site.

-

Important: This schedule is tentative, and may be - subject to change.

-

General discussions about the pending release and known issues should be sent to the public freebsd-stable mailing list. MFC requests should be sent to re@FreeBSD.org.

&beta.local.where; &beta2.local.where;

Schedule

- +
Action Expected Actual Description
Initial release schedule announcement - 26 February 2015 Release Engineers send announcement email to developers with a rough schedule.
Release schedule reminder 20 May 2015-21 May 2015 Release Engineers send reminder announcement e-mail to developers with updated schedule.
Code slush begins 19 June 2015 - Release Engineers announce that all further commits to the &local.branch.stable; branch will not require explicit approval, however new features should be avoided.
Code freeze begins 3 July 2015 - Release Engineers announce that all further commits to the &local.branch.stable; branch will require explicit approval. Certain blanket approvals will be granted for narrow areas of development, documentation improvements, etc.
BETA1 builds begin 10 July 2015 - First beta test snapshot.
BETA2 builds begin 17 July 2015 - Second beta test snapshot.
BETA3 builds begin * 24 July 2015 - Third beta test snapshot.
&local.branch.releng; branch 31 July 2015 - Subversion branch created; future release engineering proceeds on this branch.
RC1 builds begin 31 July 2015 - First release candidate.
&local.branch.stable; thaw 1 August 2015 - The code freeze on the &local.branch.stable; branch is lifted.
RC2 builds begin 7 August 2015 - Second release candidate.
RC3 builds begin * 14 August 2015 - Third release candidate.
RELEASE builds begin 21 August 2015 - &local.rel;-RELEASE builds begin.
RELEASE announcement 31 August 2015 - &local.rel;-RELEASE press release.
Turn over to the secteam - - &local.branch.releng; branch is handed over to the &os;  Security Officer Team in one or two weeks after the announcement.

"*" indicates "as-needed" items.

Status / TODO

&os; Release Engineering TODO Page

Additional Information